> For the complete documentation index, see [llms.txt](https://docs.idew.org/project-video-game/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://docs.idew.org/project-video-game/project-instructions/2-design-and-build-solution.md).

# 2 DESIGN & BUILD SOLUTION

This phase of the project will require about 6-7 weeks to complete. Your teacher will identify the specific deadline(s) for the task assignments.

| Task                          | Non-Block Periods | Block Periods | ✓ | ✓+ |
| ----------------------------- | ----------------- | ------------- | - | -- |
| 2.1 Project Schedule          | 1                 | 1             |   |    |
| 2.2 Game Design Document      | 5                 | 3             |   |    |
| 2.3 Paper Prototype           | 3                 | 2             |   |    |
| 2.4 Playtest Paper Prototype  | 3                 | 2             |   |    |
| 2.5 Game Code                 | 15-20             | 10-13         |   |    |
| 2.6 Game Assets               | (15-20)           | (10-13)       |   |    |
| 2.7 Internal Playtesting      | (15-20)           | (10-13)       |   |    |
| **2.8 Solution Presentation** | 3                 | 2             |   |    |

**NOTE:** Tasks 2.5, 2.6, and 2.7 should be completed in parallel to each other.