2 DESIGN & BUILD SOLUTION

This phase of the project will require about 6-7 weeks to complete. Your teacher will identify the specific deadline(s) for the task assignments.

Task

Non-Block Periods

Block Periods

✓+

2.1 Project Schedule

1

1

2.2 Game Design Document

5

3

2.3 Paper Prototype

3

2

2.4 Playtest Paper Prototype

3

2

2.5 Game Code

15-20

10-13

2.6 Game Assets

(15-20)

(10-13)

2.7 Internal Playtesting

(15-20)

(10-13)

2.8 Solution Presentation

3

2

NOTE: Tasks 2.5, 2.6, and 2.7 should be completed in parallel to each other.